Here are some views of the KIPO tower site project on Pu`u O`hia (Tantalus), O`ahu.
This project is nearly 20 years in the making, and will finally be complete in the fall of 2008.
The new KIPO tower site is located directly above Honolulu, at over 2000 feet above sea level.
The idea of relocation to this site came from Robert Leembrugen, former chief engineer of HPR.
It took many years of negotiation and patience to bring the project to completion.
Delivery of the new generator
The generator, being wired up
The new Nautel V10, moved into the building
The transmitter with all modules installed
The new transmitter and racks
More Progress on Sepetmber 10, 2008
The new transmitter, now operational
STL and monitoring gear
The KIPO transmitter system, finished for the moment.
More transmitters, a multi-station combiner and other features are coming in the future,
This page was updated on September 20, 2008